14th April 2021: Tender No: MOD/INFRAS/024/20/21
To: All Prospective Bidders
Addendum/Clarification No: 2
Following the issuance of the RFQ on the 18th of March 2021; Issuance of Addendum No:1 on 6th April 2021 and the Pre-bid meeting/Investor Conference held on 13th April 2021, Prospective Bidders are advised of the extension of time for the return of the RFQ Bids by 7 (Seven) days. As a result, the RFQ Bids are now to be returned by 1200hrs EAT on the 5th of May 2021. Consequently, the new indicative target timeline for the conclusion of the procurement process is as set out below:
Date | Activity |
18th March 2021 | Issuance of Request for Qualification (RFQ) |
13th April, 2021 | Pre-bid meeting/investor Conference |
5th May, 2021 | Return of RFQ bids |
12th May, 2021 | Evaluation of RFQ bids |
26th May, 2021 | Notification/Publication of Shortlisted Bidders |
10th June, 2021 | Issuance of Request for Proposals (RFP) |
10th August, 2021 | Return of RFP bids |
20th August, 2021 | Evaluation of RFP bids |
26th August, 2021 | Appointment of Preferred Bidder |
27th September, 2021 | Conclusion of Contract Negotiations |
11th October, 2021 | Signing of contracts |
This Addendum/Clarification No. 2 (Two) shall be deemed to be part of the RFQ. All other conditions in the RFQ remain the same.