TENDER NO: MOD/INFRAS/024/20/21 ADDENDUM/CLARIFICATION NO: 3

TENDER NO: MOD/INFRAS/024/20/21 ADDENDUM/CLARIFICATION NO: 3

20th April 2021

Tender No: MOD/INFRAS/024/20/21

 

Project: Financing, Design, Construction and Commissioning of Residential Accommodation for the Kenya Defence Forces on a Build-Lease-And-Transfer (BLT) Basis

To: All Prospective Bidders

 

Addendum/Clarification No: 3

 

Following the issuance of the RFQ on the 18th of March 2021; the issuance of Addendum No:1 on 6th April 2021, the Pre-bid meeting/Investor Conference held on 13th April 2021, the issuance of Addendum No:2 on 14th April 2021; Prospective Bidders are advised to take note of the response to queries and request for clarifications during the virtual Pre-bid meeting/Investor Conference held on 13th April 2021, as well as the response to queries and request for clarifications made subsequent to 13th April 2021, to date.

RESPONSE TO QUERIES AND REQUEST FOR CLARIFICATION DURING THE VIRTUAL INVESTORS/PRE-BID CONFERENCE HELD ON 13TH APRIL 2021

 

S/No. Section Question Response
1. Project      Land

Acreage      and Project Sites

(1) What is the total acreage available for construction? a) The acreage set aside for housing is as follows: i.Roysambu – 15 acres, ii.Kwambuzi (Nanyuki) – 300

acres,

iii.Nyali Barracks – 10 acres, iv.Lanet Barracks – 21 acres,

and

v.Gilgil Barracks – 200 acres.

 

b) Bidders will be expected to optimize land usage in their designs that will form part of their RFP bids.

(2) The 200 acreage in Gilgil, does this mean that we can use the whole 200 acres in the housing project or this is just the whole camp and the housing project will be a small allocated portion of it? The 200 acres has been demarcated for housing purposes. For this first phase of the project, it is expected that the units constructed will utilize a portion of the 200 acres. This also applies to the other sites.

 

S/No. Section Question Response
    (3) After agreement signing, will the CA provide land for purpose of construction right away or not? The Ministry of Defence will make land available for construction of the proposed project upon contract execution.
(4) The CA refers to the leasing land in the tender documents, Will the ProjectCo. pay the rental fee or CA will provide land for free? The Ministry of Defence will make land available for construction of the proposed project at No Cost. Hence, the ProjectCo (Bidder) is not expected to pay leasing fees.
(5) The document states that we will be leasing land from KDF – what is the land leasing rate from KDF
(6) Can     you     provide     the valuation of each parcel of

land?

a)      The land parcels for the project are not available as collateral to prospective lenders to the ProjectCo. However, the anticipated security package for the proposed project includes the Quarterly Lease Payments under the Project Agreement; the Direct Agreement between the GOK and lenders and the GOK Letter of Support.

 

b)      Under the proposed contractual structure, the land lease to the ProjectCo will be at peppercorn. As a result, the stamp duty will be negligible in value.

 

c)       No refund from either party is anticipated under the contractual structure. The payment flow will be entirely quarterly lease payments paid to the ProjectCo by The MoD

and capital contributions

(7) Can you provide the valuation of each parcel of land and can that asset be offered as a counter guarantee to the lender?
(8) Will the developer still pay stamp duty for land upon transfer? If so, MOD should advise on land value for financial calculations.
(9) Kindly if advise if the land parcels for the project can be charged to the financier to facilitate raising of project finances?
(10) Please confirm if the land for the project can be charged to financier to enable capital raising?
(11) For the purposes of refund,

which  type  of  refund will

 

S/No. Section Question Response
    the CA adopt to make the refund more reliable?

(12) If CA will use their land as a guarantee, will a bank provide a counter- guarantee or a bank security?

during       the       construction period.
(13) With all the parcels of land that you have mentioned, is there a master planning aspect for the parcels? There exist master plans for all The MoD land.
(14) Is the land owned by KDF? Yes, all the parcels of land for the five sites are owned by KDF.
2. Ancillary Facilities     and Infrastructure (1) The Ancillary facilities sometimes can be very expensive e.g., the Mess, officers center, sports facilities. Will these be paid directly on completion or it will be part of the BLT? a)      The Preliminary Information Memorandum (PIM) sets out a broad description of existing infrastructure and amenities. At the RFP stage, shortlisted bidders will have an opportunity to visit the sites and assess existing infrastructure prior to submission of their RFP bids.

 

b)      Ancillary facilities and infrastructural requirements of each project site are expected to be accommodated within the financing envelope as described in section 4 of the Preliminary Information Memorandum (PIM).

(2) Have you considered providing facilities such a mall and children’s playing ground for each project site for the residents and children?
(3) Is there a boundary perimeter wall for each project site required?
3. Lots (1) Can the investor apply for a single lot or it is mandatory for application of the whole project? The RFQ is for a single project with five sites. It is not the intention of The MoD to unbundle the project into lots. Bidders are, therefore, advised to treat

 

S/No. Section Question Response
    (2) Can we choose one site rather than all the available sites? the project as such. Consequently, the winning bidder will be expected to design, build and finance the housing units across the five (5) sites and deliver them within the two-year construction period.
(3) Can the investor apply for one or two lots, instead of the whole project?
4. Quarterly Payments (1)    Is there any assurance by form              of              an undertaking/performance guarantee from the Ministry to ensure that the quarterly payments are not delayed?

 

(2)    Delay in these payments is very   risky   for    the    EPC

contractor.

a)      The MoD anticipates no delays in the quarterly payments. These quarterly payments are accumulated from the monthly housing allowances of the officers’ salaries which are normally paid on time without any delays.

 

b)      In the unlikely event of delay, reference will be made to the default interest rate of the senior lenders to the ProjectCo as per their financing agreement.

 

c)       The project duration is 15 years with 2 years for construction. During the 2- year construction period, a quarterly capital contribution equivalent to KES 125Million will be made in arrears. Post- construction, quarterly lease payments of KES 125Million will be paid to ProjectCo for the remaining project term of 13 years. As a result, the total outlay for capital contributions and quarterly lease payments is KES 7.5Billion and not KES 6.5Billion.

(3) Please, could you confirm guarantee for the KES 125M over the 15 years?
(4) Please advise if there is a delay in the quarterly Kshs

125 million what rates of interest will be applied on the delay

(5) Can you kindly clarify as to why the lease payments are to cater for 52 quarters, equivalent to 13 years while the lease period is 15 years?
(6) Can you please clarify about the quarterly payments of 125 million for 52 quarters as the total works out to KES

6.5 billion?

(7) What is the rationale of charging rent – are you

 

S/No. Section Question Response
    going to put a cap on rent or allow market rates? d)      Upon construction completion, The MoD will offtake all residential units and guarantee quarterly lease payments whether the units are occupied or not. For emphasis, the ProjectCo will not take occupancy risk.

 

e)      The quarterly payment of KES 125million is fixed for the entire project duration. The source of funding for the quarterly payment is from the housing allowance of KDF officers whose salaries are relatively static. However, indexation of the quarterly payment is addressed in S/No. 8 and 9 below.

(8) Can the Housing allowance rates for the different cadres to be accommodated in these units be shared?
(9) Is there an arrangement to guarantee uptake of units since lease payments will be made from house allowances?
(10) Is there headroom to increase the lease payments?
(11) Since rental deduction could potentially rise within

15 years, will this be reflected on the quarterly payments as well?

5. Performance Security On Payment Performance Guarantee, the question which was not answered is whether the instrument of Performance Guarantee will be issued. As security for the performance of its obligations during the construction period, the ProjectCo will provide to the contracting authority an irrevocable and unconditional guarantee from a bank.
6. Capital contribution (1) Since the Government is making a capital contribution, one would expect that bidders will be required to achieve a minimum rate of return on the project. Will bidders be expected to meet such a hurdle rate in their financial

Modelling?

a)      The capital contribution will be towards the financing of construction. It is for the Bidders to determine what rate of return is commensurate to the risk they are assuming by participating in this project, given the financing mechanism outlined in S/No. 4 above.

b)      The capital contribution will be released to the Project Company that will be formed

(2) You      state      that       the contribution  from  MOD will

be 1 billion. When will this

 

S/No. Section Question Response
    amount be released to the contractor? by the winning bidder on a quarterly basis in arrears and is intended to be in sync with construction progress.

 

c) The MoD financial headroom  is fixed since the profile of cashflows are derived from monthly housing allowance deductions from salaries. In the event that the construction is completed in under two years, the undrawn capital contribution will be paid as a capital contribution in arrears.

(3) Is the 1 billion paid in a single tranche or 4 instalments of 125 million every quarter?
(4) Is the 1 billion-shilling MoD contribution to be distributed across all the square meters or is it per bidder.
(5) Are the quarterly payments over the 2-year construction period be on milestone basis or time based only?
(6) Is there a marking system applicable and any incentives for completing the project at a faster rate say in 18 months instead of 24 months, as an example?
(7) If the payments are based on housing allowance deductions and the construction happens in less than the predicted time of 2 years, can the payments also start earlier?
(8) If the project is completed before 2 years does this mean the 125m per quarter will be increased as per the percentage completed?
7. Taxes (1) Clarification if the lease rentals will be subject to relevant taxes. The quarterly payment is an all-in lease payment inclusive of all applicable taxes. No tax exemptions/incentives are anticipated as at the time of the RFQ. It is for the
(2) Please    clarify   about    the

quarterly  payments  of 125

 

S/No. Section Question Response
    million for 52 quarters is including 16% VAT or not? Bidders to undertake their own tax structuring so as optimize their returns within the tax framework of the country.
(3) Does the project qualify for tax concessions or incentives like the AHP by the ministry department of housing?
(4) Any Tax exemptions for this Project
(5) Shall the project company have subsidies to deliver project in terms of tax holidays and another implementation required thereof
(6) Will there be a custom duty waiver for this project?
8. Inflation Adjustments (1) Will the lease payments be adjusted to cater for inflation? As at the issuance of the RFQ, the quarterly payments are assumed to be an all-in lease payment inclusive of inflation adjustments. However, a more definitive position will be arrived at prior to issuance of the RFP to shortlisted bidders
(2) Is there scope for inflation during the 52 quarters?
(3) Has inflation been considered on the KES 125 million per quarter for 52 quarters?
9. Foreign Exchange (Forex) Adjustments (1) Since the borrowing for financing is in foreign currency, say, US Dollars, can the quarterly payments totaling 6.5 billion plus the 1 billion be paid in equivalent USD or converted at a fixed exchange rate applicable on the closing date of the bid or the date of contract signing? As at the issuance of the RFQ, the quarterly payments are assumed to be an all-in lease payment inclusive of forex adjustments. However, a more definitive position will be arrived at prior to issuance of the RFP to shortlisted bidders

 

S/No. Section Question Response
    (2) Can losses incurred due to currency fluctuation be compensated to the contractors and provisions included in the contract?  
(3) Since the financing will be obtained in hard currencies and the income in terms of lease will be in KES. Is there a provision for hedging USD/GBP/EUR/JPY against KSH?
(4) Incase financing is from an International Bank; it will be hard currency. Kindly address the forex risk
10. Letter of Support (LOS) (1) The            Letter            of Support/Comfort, does that include a sovereign guarantee? a)      The Letter of Support (LOS) is not a Sovereign Guarantee. Sovereign Guarantees are limited to borrowings by GOK and this transaction is not a debt transaction for the GOK. The intention is to issue an LOS, which is designed to underwrite political and defined commercial risks in a particular transaction. Access to key heads of terms of the GOK Letter of Support will be available at RFP stage. However, Broad principles of LOS are espoused in the GSM policy available on the National Treasury website.

 

b)      It is not the intention of The MoD to issue a Standby Letter of Credit.

(2) Kindly advise if a copy of the Letter of Support can be provided
(3) Can the ministry issue a Standby Letter of Credit or is it just a Letter of Support?

 

S/No. Section Question Response
11. Project Agreement (1) When signing the contract agreement, will the CA allow ProjectCo, to revise some conditions of the contract as some of them may not be consistent with the actual

situation?

a)      The draft project agreement will form part of bidding documents at RFP stage for consideration of shortlisted bidders. Contractual issues will thereafter be open for full negotiations with the preferred bidder.

 

b)      The Operation and Maintenance (O&M) of project assets is excluded from the scope of the Project Agreement. This will be the sole responsibility of the Ministry of Defense.

 

c)       The term of lease starts on contract signing.

(2)    After completion of construction, who will be responsible for the payment of the maintenance and management period of the Project?

(3)    Will these be included in the contract price of the agreement?

(4)    If to be considered separately, what is the estimate?

(5) When does the 15-year lease period start? Does it start at contract signing or when the units are being constructed?
12. Refinancing Please provide scope for refinancing event after rental stabilization In principle refinancing is permitted subject to fulfillment of certain conditions that the Project Agreement will prescribe.
13. Build Lease Transfer (BLT) Model (1) As the project is a BLT Model, kindly clarify on transfer – how will the transfer occur Under the BLT structure, the MoD will lease the project sites to the ProjectCo which will undertake construction of the project housing. Upon completion of construction, the ProjectCo will lease back the project housing to the MoD for the remaining term of the agreement. Upon expiry of the Project Agreement the derivative lease and lease back agreements will terminate automatically. The details of the hand back  regime  will  be  set  out  in the

Project Agreement a draft of which will

(2) This is a BLT Model. Can you clarify something about the Transfer?
(3) Upon the termination of lease term, all the units will

 

S/No. Section Question Response
    be transferred to KDF for free? be made available to the shortlisted bidders.
14. Project Finance (1) How will the CA consider the recourse project financing if our bank insists on limited recourse project

financing?

a)      It is a requirement under section 3.2 of the RFQ that the bidder                demonstrates experience of having raised non-recourse or limited recourse financing. Any other type of financing previously raised by the bidder will not meet the qualification requirements.

 

b)      Yes, a financier can support more than one bid provided they are not a Member of any bidding consortium.

 

c)       It is for the bidders to arrange the required financing to deliver the project.

(2) Can one financier support multiple bidders?
(3) Can a developer have their own arrangement with a bank?
15. Net       Present Value (1) Has the PPP Unit tested the

125 million per quarter to establish a positive NPV?

It is for the bidders to optimize the parameters put forward in the project structure, including the construction costs; number of housing units and the cost of debt, to achieve their desired rate of return within the MoD’s financing envelope of KES 7.5Billion over the 15-year project term.
(2) Has the PPP Unit considered whether the 125 million lease payment of 52 quarters achieves a positive NPV?
16. Project Value Do we assume that the project value is around KES6.5 billion? It is for the bidders to generate the project costs estimates based on their designs and approach to the delivery of the output specifications within the financing envelope detailed in S/No.15 above.

 

S/No. Section Question Response
17. Special Purpose Vehicle (SPV) (1) Please expound more on the

SPV?    When    will    apply, define the preferred set up?

a)      The PPP Act 2013 requires that a successful bidder shall establish a ProjectCo in accordance with the Companies Act for the purpose of undertaking the project. Bidders are NOT required to register a Special Purpose Vehicle (SPV) at RFQ and RFP stage. The SPV is a requirement prior to Financial Close by the preferred bidders and their various shareholders.

 

b)      The MoD will make a capital contribution without taking a stake in the SPV.

(2) If this is the case, will there be a creation of an SPV?
(3) Can the KES 1 billion be considered as equity contribution?
(4) Is there a requirement for the SPV shareholding to be fully subscribed by commercial or financial close
(5) Bidder not willing to take on debt on their balance sheet as such set up an SPV together with the bank and MoD
(6) Will the SPV need to be registered before the 27th of April 2021
18. Bidder Qualifications

Bidder

(1)    Can one accumulate the contract price of financing project with some different projects within last 15 years?

 

 

(2)    Consider – A project with the financing of 100 million USD should be a mega project and difficult to find for most contractors.

 

 

(3)    Must one provide EPC management experience which is fully completed or substantially completed?

In response to the queries on bidder qualifications the following adjustments have been made to the RFQ:

 

a.       3.1 is revised downwards from 120,000sq.m of greenfield residential accommodation to 40,000sq.m of the same typology and a minimum project investment requirement of USD50Million.

 

b.       Under 3.2, the lead developer has to demonstrate that they have successfully raised at least USD 50Million in non-recourse or limited recourse debt and

 

S/No. Section Question Response
    (4) They say the technical qualification is 120,000sqm of build space in the last 15 years. Is this a single project or cumulative projects? USD25Million in equity for each of at least two Greenfield projects.

 

c.       The qualifications cited in 1 and 2 above should be within the last 15 years and are not in aggregate or cumulative.

 

d.       The EPC management requirements remain the same. However, where a project developer has employed a project manager to oversee the management of the EPC contractor such experience will qualify and should be cited as such.

(5)  Bidder  Qualification Criteria

3. Project Experience and Technical Capability 3.2 Project financing experience

– Requirement of having raised debt of USD 100 million and equity of USD 50 million for at least 2No. Greenfield Projects.

This requirement is too high for single projects as explained for 3.1 above.

(6) Can the focus be on the Bidders proof of ability to raise the required funding for the project instead e.g., Financier’s Letter of Support etc.?
(7)    Bidder Qualification Criteria

3. Project Experience and Technical Capability 3.3 EPC management experience – Requirement of having successfully executed as a project owner or supervised an EPC contractor’s execution of the construction of at least two Greenfield Residential Accommodation Projects of similar scope.

 

(8)    Kindly make the

requirement         to         be aggregate of developments.

 

S/No. Section Question Response
    (9)    Bidder Qualification Criteria

3. Project Experience and Technical Capability 3.1 Financial capability for project development

 

(10)                       Requirement of residential accommodation project in the order of 120,000sq.m and minimum investment of $100 million.

 

(11)                         This requirement is too high. Probably none or very few, if any single such development undertaken in Kenya as a developer would prefer to phase or undertake several projects to minimize market risk.

 

(12)                       Kindly make the requirement to be aggregate of developments, both residential and commercial and half the requirements.

(13)                       For the requirement on EPC management experience can we have the project  management company experience that has supervised the EPC contractor?

(14)                       Page 12 on EPC management experience: It states that the project needs to achieve commercial operation, does that mean the project must be a commercial project? Can it be a self- development project?

 

 

S/No. Section Question Response
    (15)                        Under the clause of project  financing experience, it states that the leader member shall within the 15 years, raise at least 100 million USD and 50 million USD in equity for two projects.

 

(16)                        Can the lead member raise 150 million USD for the project rather than introducing 50 million USD in equity pools raising

100 million USD for the project?

 
19. Contractor, Sub Contractor and

Supplier

(1)    The experience and resources of Bidder’s contractors shall not be considered in determining the Bidder’s compliance with the qualification criteria contained in this RFQ.

Is any consideration behind this clause?

 

(2)    If Contractor’s experience cannot be considered in determining the Bidder’s compliance with the qualification, how can the bidder meet the construction qualification

requirements?

a)      The experience and resources of Bidder’s contractors shall not be considered in determining the Bidder’s compliance with the qualification criteria contained in this RFQ if they are NOT members of the bidding consortium. The same applies to suppliers and sub- contractors.

 

b)      The bidder has the discretion of having one or multiple contractors/ subcontractors/ suppliers.

 

c)       The RFP stage will require certain disclosures on the methodology. Details on how to disclose local contents will be provided at that RFP stage.

(3) Will the constructions across all the sites be sourced from one contractor or you shall have multiple selection of contractors / bidders?
(4) Can     a     bidder     appoint multiple sub-contractors?

 

S/No. Section Question Response
    (5) Must the contractor disclose local subcontractor at the time of bidding?  
(6) Can a sub-contractor be part of multiple consortia bids?
(7) Is                 subcontracting acceptable?
(8) If a supplier of construction material is part of a consortium that bids, can he also be the supplier of another consortium he is not a member?
20. Specifications (1)    Is there a preferred building material or it is up to the contractor to get creative?

 

(2)    Are we allowed to give the specification on quality of the units and design concepts?

 

(3)    Can you offer prefab panel construction technology?

 

 

(4)    Can you build 4 storey housing units instead of single dwelling bungalows?

 

(5)    Can you consider provision of internet connectivity to each housing unit say through fiber connection to each household?

a)      The RFQ does not prescribe the building technology and material. The MoD encourages alternative                  building technology that can deliver the most housing units as per the output specifications but within the proposed financial headroom of capital contribution and quarterly payments.

 

b)      Creative approaches to the delivery of the project are encouraged that optimize the use of land whilst meeting or exceeding the minimum specifications requirements.

 

c)       Yes,            electromechanical designs are to provide for internet connectivity in the units.

21. Lead Developer (1) Kindly     clarify    the     lead developer:   Can   the  lead

developer     be     an     EPC

(a) The RFQ does not prescribe the   nature,    character and

background     of     the    Lead

 

S/No. Section Question Response
    contractor? Or does it have

to be the financier or fund provider for the project?

Member. The Lead developer can be any member of the consortium provided they meet the lead member criteria of 35% shareholding in the Project Company and the associated net worth requirements.

 

(b) Currently, the RFQ is open on change of shareholding but it is anticipated that the lock-in period will be prescribed in the draft Project Agreement to be issued at the RFP stage.

(2) Does the 35% need to be an Industrial or financial partner?
(3) Can the lead Member will have a less than 35% of the equity shareholding of the Consortium?
(4) Can the lead member change the shareholding during the SPV formation to less than the 35%?
22. Greenfield Project (1)    Please clarify the definition of greenfield project

a)    Can greenfield project be an infrastructure project or it has to be a building project? b) Can an EPC project be deemed as a greenfield  project?  c) Does the greenfield project have to be an investment

project?

a)      Refer to page 8 of the RFQ.

 

b)      Greenfield project is defined in the RFQ. For a project to be considered as a Greenfield project, the bidder must have prepared the proposal, negotiated the agreement, reached commercial close and raised non-recourse project financing to deliver the project.

 

c)       If one has acquired a brownfield by way of design, negotiation or raising financing, this is not a Greenfield project.

Greenfield project has to be a housing project; can it be a railway project?
23. Local Content (1) Does the 40% local content apply as per the procurement law and is there any preference given

to citizen contractors?

a) There are two procurement laws in Kenya – Public Procurement and Asset disposal  Act  and  the  Public

Private Partnership Act. Under

 

S/No. Section Question Response
    (2) Is there a preference in the evaluation to 100% Kenyan consortia? the PPP Act there are no specified minimum local content requirements.

 

b) This Project is procured under the PPP Act which has no local content minimum requirement under the PPP Act and it’s not a scoring parameter. However, the PPP encourages partnerships that promote local participation including the Buy Kenya Build Kenya philosophy.

(3) Is there a 40% local content requirement in the consortium? If so, in what ways?
(4) Any incentive for the local developer?
(5) Can 2 – 5 local developers be allowed to come together and bid as one?
24. Net Worth The net worth requirements are not favorable to local developers. The Project requirement is for the developer to have capacity to raise the project funding. Based on the letter of support and the committed cash flows from the 125m payments the Net Worth requirement is too high as it is not required for the capital raising. Local companies have capacity to raised up to $100m however their net worth is not so high We request the Ministry to review these conditions to better favor local developers Minimum Net worth requirements for members has been revised downwards to USD 25Million and the Lead Member net worth to USD12.5Million and have a minimum of 35% of the equity shareholding of its consortium.
25. Defects Liability Period (DLP) (1) Kindly    expound     on    the defect  liability  period   and

how it affects the developer

a)      The law requires a DLP period of 12months. During this period the Project Company will be required to fix latent defects.

 

b)      Post construction – Operation and Maintenance will be The MoD’s responsibility.

(2) The period spanning 15 years from the project agreement, does it include the DLP (Defect Liability Period)
(3) What obligations / performance standards may be required from the Service

Provider   during   the  post

 

S/No. Section Question Response
    construction phase? We note that the O&M of the units will be undertaken by the MOD as mentioned during the presentation.  
26. Construction Cost Is there an estimate of the building construction cost per square meter, expected? In the GOK housing projects it was given at USD 300 per sqm. The cost per square meter is open and at the discretion of the bidders. Bidders are encouraged to be efficient in their cost of construction to optimize the number of units developed.
27. Utilities Do all the parcels of land plots have power, water and road infrastructure or is that the responsibility of the contractor and can the topography and the GPS coordinates be provided, respectively? a)      This is part of the project scope to the extent necessary per site as indicated within the PIM document. A more detailed assessment will be undertaken for the individual sites at RFP stage on existing infrastructure.

 

b)      The MoD will facilitate site visit for shortlisted bidders to conduct due diligence in submitting their proposals.

28. Furniture    and fittings (1) Are there any pieces of furniture, furnishings and fittings for kitchen, bathroom etc. to be provided in each housing unit? Furnishing of the housing units will be done by The MoD but the built-in fittings such as bathrooms, washrooms and cupboards are expected of the Project Company.
(2) Should the developer also provide furniture and kitchen laundry kits?
29. Import Restrictions Are there any restrictions on import of material from a particular country? There is no restriction on importation of materials.
30. Land vs Built- up Ratio (1) Is there a defined/proposed

structure outlining Land vs- built area ratio preference?

There  is  no  hard  defined/proposed

structure outlining land vs built-up area ratio preference but optimization

 

S/No. Section Question Response
     

(2) To guide on design/concept development.

of land utilization and creative designs are acceptable.
31. ESIA,

Geotechnical Studies        and Statutory Approvals

(1) Are contractors required to undertake geotechnical studies and environmental & social impact assessment study to be approved by NEMA for each project? It is the responsibility of the ProjectCo to undertake all relevant studies. However, The MoD will facilitate the process leading to the granting of statutory approvals.
(2) Will the MOD cater for the statutory approvals for the projects?
32. Contact Information Can we please be provided with a list of all the panel members and attendees including names and title and contact phone numbers? All             communication             and correspondences should be in the manner articulated in the procurement documents in compliance with RFQ rules of engagement.
33. Bid extension (1)    Is it possible for us to have an extension of two weeks?

(2)    We kindly request a 30-day extension to the submission date in light of all the clarifications and to allow the financiers to do the necessary due diligence on the projects

The RFQ period has been extended by one week to 5th May 2021.

 

 

This Addendum/Clarification No. 3 (Three) shall be deemed to be part of the RFQ. All other conditions in the RFQ remain the same.

PRINCIPAL SECRETARY MINISTRY OF DEFENCE

Add Comment

Your email address will not be published. Required fields are marked *

X-Frame-Options: SAMEORIGIN
Skip to content